Building Permit Fees

(Based on Completed Cost of Construction)
Effective as of January 17, 2023

Construction CostsFee
$0-$40,000$200.00
$40,001-$50,000$200.00 for the first $40,000 plus $5.00 for each additional $1,000, or fraction thereof, to and including $50,000
$50,001-$100,000$250.00 for the first $50,000 plus $5.00 for each additional $1,000, or fraction thereof, to and including $100,000
$100,001 -$500,000$500.00 for the first $100,000 plus $5.00 for each additional $1,000, or fraction thereof, to and including $500,000
$500,001-$1,000,000$2,500.00 for the first $500,000 plus $5.00 for each additional $1,000, or fraction thereof, to and including $1,000,000
$1,000,001+$5,000.00 for the first $1,000,000 plus $5.00 for each additional $1,000, or fraction thereof

Factory Built Home, Manufactured Homes and Mobile HomeFee
Permanent Foundation$125.00 per section $250.00 minimum
Any mobile home not requiring a conditional use$150.00
Temporary Foundation$250.00
Trailer Park$150.00

Other Inspections and FeesFee
1. Inspection outside of normal business hours$50.00 per hour*
2. Reinspection fees assessed under provisions of Section 108.4$30.00 per hour*
3. Inspection for which no fee is specifically indicated$30.00 per hour*
4. For use of outside consultants for plan checking and inspections, or bothActual Cost**
5. For issuance of each temporary Certificate or Occupancy$250.00***
* Or the total hourly cost to the jurisdiction, whichever is the greatest. The cost shall include supervision, overhead, equipment, hourly wages and fringe benefits of the employees involved.
** Actual Costs include administrative and overhead costs.
*** $100.00 shall be refunded if a Certificate of Occupancy is issued prior to the expiration.
**** Fees may be doubled for Zoning and Building Permits if not obtained prior to start of construction.

AcreageFee
** Administrative Review$300.00
Up to 10.9 acres$550.00
11-20.9 acres$575.00
21-30.9 acres$600.00
31-40.9 acres$625.00
41-59.9 acres$650.00
60 acres +$650.00
    Plus $15.00 per 40 acres or fraction thereof in excess of 60 acres$15.00

Miscellaneous Building Permits:Fee
RemodelBased on actual labor and material valuation
Reroofing$150.00
Mechanical$150.00
Demolition$50.00
House Moving$50.00

AcreageFEE
Up to 10.9 acres$725.00
11-20.9 acres$800.00
21-30.9 acres$875.00
31-40.9 acres$950.00
41-59.9 acres$1,025.00
60 acres +$1,025.00
Plus each additional 40 acres or fraction thereof over 60 acres$20.00

ApplicationAdministrativeFull Review
Appeal $350.00
Campground see Planned Development
Certificate of Designation $500.00
Combination of Lots Agreement$200.00 
Conditional Use$200.00$500.00
Conditional Mobile Home Placement$250.00$500.00
Exemption from Subdivision$300.00$500.00
Amended Exemption$200.00$300.00
Floodplain$150.00 
Replat of Subdivision $550.00
Mobile Home Placement$150.00 
Pre-Application Conference n/c
Rezoning $750.00
Sign Placement$75.00 
Special Use $650.00
*For Wind, Solar and BESS, see the Wind, Solar and BESS fees section.
Amendment to Special Use$200.00$650.00
Variance$150.00BCC - $250.00
BOA - $500.00
Vesting of Property Rights $200.00
1041 Regulation $5,000.00
Zoning Permit (non residential -
non-commercial construction)
$150.00 
Boundary Line Adjustments$200.00 
Amended Plats*$400.00*Right of Way, Easement, Vacation,
Change to Condition of Approval(s),
or Plat Note
All Other Amended Plats$200.00 
Plat Correction$200.00 
Replat$400.00 
Plat Vacation - No Public Infrastructure
or Dedication
$400.00 
Plat Vacation - Public Infrastructure or
Dedication
$400.00 
Temporary Uses and Structures$200.00 

Exemptions$13.001st page Mylar$10.00 additional pages of Mylar
Minor Subdivision$13.001st page Mylar$10.00 additional pages of Mylar
Planned Development$13.001st page Mylar$10.00 additional pages of Mylar
Covenants$13.001st page$5.00 additional pages

DescriptionFee
Building Mounted Wind Energy Facility Application Fee$150.00
Ground Mounted Wind Energy Facility Application Fee$1.00/acre
(Minimum $5,000)
     Permit Fee$1,000.00/MW
Accessory Ground Mounted & Building Mounted Solar 
Collectors Facilities - Residential - Application Fee$500.00
Accessory Ground Mounted & Building Mounted Solar 
Collectors Facilities - Non-Residential / Fewer than 2MW - Application Fee$1,000.00
Principal Solar Collectors - Application Fee$1.00/acre
(Minimum $5,000)
     Permit Fee$1,000.00/MW
BESS - Application Fee$1.00/acre
(Minimum $5,000)
     Permit Fee$1,000.00/MW

CostFee
Non-residential / Non-commercial Construction Fee$150.00