0

Permit Fees

#FFFFFF

FEES SUBJECT TO CHANGE WITHOUT NOTICE.
All fees doubled for special hearing.

Building Permit Fees

(Based on Completed Cost of Construction)
Effective as of January 17, 2023

Construction Costs Fee
$0-$40,000 $200.00
$40,001-$50,000 $200.00 for the first $40,000 plus $5.00 for each additional $1,000, or fraction thereof, to and including $50,000
$50,001-$100,000 $250.00 for the first $50,000 plus $5.00 for each additional $1,000, or fraction thereof, to and including $100,000
$100,001 -$500,000 $500.00 for the first $100,000 plus $5.00 for each additional $1,000, or fraction thereof, to and including $500,000
$500,001-$1,000,000 $2,500.00 for the first $500,000 plus $5.00 for each additional $1,000, or fraction thereof, to and including $1,000,000
$1,000,001-$+ $5,000.00 for the first $1,000,000 plus $5.00 for each additional $1,000, or fraction thereof

Factory Built Home, Manufactured Homes and Mobile Home Fee
Permanent Foundation $125.00 per section $250.00 minimum
Any mobile home not requiring a conditional use $150.00
Temporary Foundation $250.00
Trailer Park $150.00

Other Inspections and Fees Fee
1. Inspection outside of normal business hours $50.00 per hour*
2. Reinspection fees assessed under provisions of Section 108.4 $30.00 per hour*
3. Inspection for which no fee is specifically indicated $30.00 per hour*
4. For use of outside consultants for plan checking and inspections, or both Actual Cost**
5. For issuance of each temporary Certificate or Occupancy $250.00***
* Or the total hourly cost to the jurisdiction, whichever is the greatest. The cost shall include supervision, overhead, equipment, hourly wages and fringe benefits of the employees involved.
** Actual Costs include administrative and overhead costs.
*** $100.00 shall be refunded if a Certificate of Occupancy is issued prior to the expiration.
**** Fees may be doubled for Zoning and Building Permits if not obtained prior to start of construction.

Acreage Fee
** Administrative Review $300.00
Up to 10.9 acres $550.00
11-20.9 acres $575.00
21-30.9 acres $600.00
31-40.9 acres $625.00
41-59.9 acres $650.00
60 acres + $650.00
    Plus $15.00 per 40 acres or fraction thereof in excess of 60 acres $15.00

Miscellaneous Building Permits: Fee
Remodel Based on actual labor and material valuation
Reroofing $150.00
Mechanical $150.00
Demolition $50.00
House Moving $50.00

Acreage FEE
Up to 10.9 acres $725.00
11-20.9 acres $800.00
21-30.9 acres $875.00
31-40.9 acres $950.00
41-59.9 acres $1,025.00
60 acres + $1,025.00
    Plus each additional 40 acres or fraction thereof over 60 acres $20.00

Application Administrative Full Review
Appeal   $350.00
Campground   see Planned Development
Certificate of Designation   $500.00
Combination of Lots Agreement $200.00  
Conditional Use $200.00 $500.00
Conditional Mobile Home Placement $250.00 $500.00
Exemption from Subdivision $300.00 $500.00
Amended Exemption $200.00 $300.00
Floodplain $150.00  
Replat of Subdivision   $550.00
Mobile Home Placement $150.00  
Pre-Application Conference   n/c
Rezoning   $750.00
Sign Placement $75.00  
Special Use   $650.00
*For Wind, Solar and BESS, see the Wind, Solar and BESS fees section.
Amendment to Special Use $200.00 $650.00
Variance $150.00 BCC - $250.00
BOA - $500.00
Vesting of Property Rights   $200.00
1041 Regulation   $5,000.00
Zoning Permit (non residential -
non-commercial construction)
$150.00  
Boundary Line Adjustments $200.00  
Amended Plats* $400.00 *Right of Way, Easement, Vacation,
Change to Condition of Approval(s),
or Plat Note
All Other Amended Plats $200.00  
Plat Correction $200.00  
Replat $400.00  
Plat Vacation - No Public Infrastructure
or Dedication
$400.00  
Plat Vacation - Public Infrastructure or
Dedication
$400.00  
Temporary Uses and Structures $200.00  

Exemptions $13.00 1st page Mylar $10.00 additional pages of Mylar
Minor Subdivision $13.00 1st page Mylar $10.00 additional pages of Mylar
Planned Development $13.00 1st page Mylar $10.00 additional pages of Mylar
Covenants $13.00 1st page $5.00 additional pages

Description Fee
Building Mounted Wind Energy Facility Application Fee $150.00
Ground Mounted Wind Energy Facility Application Fee $1.00/acre
(Minimum $5,000)
     Permit Fee $1,000.00/MW
Accessory Ground Mounted & Building Mounted Solar  
Collectors Facilities - Residential - Application Fee $500.00
Accessory Ground Mounted & Building Mounted Solar  
Collectors Facilities - Non-Residential / Fewer than 2MW - Application Fee $1,000.00
Principal Solar Collectors - Application Fee $1.00/acre
(Minimum $5,000)
     Permit Fee $1,000.00/MW
BESS - Application Fee $1.00/acre
(Minimum $5,000)
     Permit Fee $1,000.00/MW

Cost Fee
Non-residential / Non-commercial Construction Fee $150.00